Local Road Reconstruction Projects

Township .. Roadway ........Location Status Bid Date
. . . . .
Fillmore 52nd Street From 140th to 141st Ave 8-27-08
Fillmore 59th Street From 142nd to 0.25 mile North 8-27-08
Gun Plain 110th Avenue From Twp Line to 10th St 7-30-08
Heath 126th Avenue From M-40 East to 38th St Complete 3-26-08
Heath 38th Street From 124th to 126th Ave Complete 3-26-08
Manlius 57th Street From 133rd to 136th Ave 8-13-08
Monterey 28th Street From Allegan Twp Line to 127th Ave Complete 4-09-08
Salem 28th Street From 142nd to 0.5 mile North Complete 4-16-08
Salem 143rd Avenue From 30th St to 0.5 mile East Under Construction 6-11-08
Saugatuck 127th Avenue From 60th to 63rd St Under Construction 4-23-08
Overisel 138th Avenue From 38th St to 0.4 mile East Complete 3-19-08
Overisel 43rd Street From 147th to Ottogan Under Construction 3-19-08



Primary Road Reconstruction Projects

Township.. Roadway .. ............Location Status. Bid Date
. . . . .
Otsego/Gun Plain 12th Street From 102nd Ave to M-89 Complete 9-28-07
Cheshire 46th Street From Baseline to 102nd Ave Under Construction 3-07-08
Martin/Wayland 124th Avenue From 12th Street to 0.5 mile East Under Construction 6-06-08




Bridge Reconstruction Projects

Township Roadway .. .............Location Status Bid Date
. . . . .
Overisel 139th Avenue 300' West of 36th Ave Complete 2-01-08



View 2007 Construction Information


Note: In order to be eligible to submit bids on any of the above projects, MDOT Prequalification is required. Plans and Specifications for these projects can be obtained from the Allegan County Road Commission office prior to the posted bid date. Please contact the Road Commission for more information.